PMP考試練習題(32)

轉載者:PMP團購網      發布時間:2012/7/18        點擊: 3683

1 The utility of network-based schedules:

  A Reveals interdependencies.

  B Facilitates “what if” exercises.

  C Highlights critical activities.

  D Provides information on resource requirements, time requirements and tradeoffs.

  E All of the above.

  ans:E

  2 The major disadvantage of a bar chart is:

  A Lack of time-phasing.

  B Cannot be related to calendar dates.

  C does not show activity interrelationships.

  D Cannot be related to manpower planning.

  E Cannot be related to cost estimates.

  ans:C

  3 The most common types of schedules are Gantt charts, milestone charts, line of balance, and:

  A Networks.

  B Time phased events.

  C Calendar integrated activities.

  D A and C only.

  E B and C only.

  ans:A

  4 Scheduling is the process by which decisions are made concerning:

  A Tasks to be accomplished.

  B Personnel/organization that will be assigned to accomplish the task.

  C Time when the tasks are to be completed.

  D All of the above.

  E A and C only.

  ans:E

  5 Time management is the allocation of time in a project's life cycle through the process of:

  A Planning

  B Estimating.

  C Scheduling.

  D Controlling

  E All of the above.

  ans:E

  6 Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:

  A $19K

  B $21K

  C $26K

  D $29K

  E indeterminate

  ans:C

  7 Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

  A Become worse, become worse

  B Become worse, improved

  C Improved, increased

  D Improved, become worse

  E None of the above are correct

  ans:B

  8 The computation for Cost Performance Index is:

  A BCWP/ACWP

  B BCWP-ACWP

  C BCWP-BCWS

  D ACWP/BCWP

  E ACWP-BCWS

  ans:A

  9 When comparing the cost of competing projects, which of the following is typically NOT nsidered?

  A Opportunity costs.

  B Direct costs.

  C Sunk costs.

  D Indirect costs.

  E Burden rates.

  ans:C

  10 The Cost Performance Index (CPI) measures:

  A cost of work performed vs planned costs.

  B work performed vs cost of work performed.

  C work performed vs planned work.

  D direct costs vs indirect costs.

  E floating costs vs. sunk costs.

  ans:B

  11 Parametric estimates are based on variables such as:

  A Detailed planning and cost restraints.

  B Physical characteristics and historical data.

  C The WBS and similar projects.

  D Project objectives and manpower allocations.

  E Precise measurements and multiple inputs.

  ans:B

  12 Cost and schedule data are usually integrated because:

  A optimized project cash flow can affect financial requirements

  B they provide MIS with an integrated system to produce reports

  C they control escalation allowances

  D they account for omissions in the definitive estimate

  E they predict future performance

  ans:E

  13 Continually measuring and monitoring the actual cost versus the budget is done to _____.

  A analyze the reasons for variances

  B establish the variances

  C identify the problems

  D All of the above.

  E None of the above.

  ans:D

  14 Using the cumulative cost curve in the special window, height B represents

  A actual cost to date

  B total budgeted costs for the project

  C planned cost for month 6

  D cost variance

  E earned value

  ans:B

  15 Value engineering/Analysis is the systematic use of techniques which does not include _____.

  A establishing values for required functions

  B provide the required functions at the lowest overall cost.

  C identifies the required function of an item

  D seeks to trade performance for cost

  E None of the above.

  ans:D

  16 The ability to achieve cost savings is inversely proportional to _____.

  A the earned value achieved to date

  B the estimated costs to complete

  C empowerment to the P.M.

  D productivity

  E None of the above.

  ans:A

  17 The estimated cost to complete (ETC) is _____.

  A BCWP/ACWP

  B the forecasted and final cost - cost to date

  C (ACWP-BCWP)/BCWP * 100

  D Total estimate - ACWP

  E None of the above.

  ans:B

  18 Considering alternate suppliers is a form of _____.

  A Value engineering.

  B Risk Analysis

  C Contract Management

  D Project integration

  E All of the above.

  ans:A

  19 You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct onclusion is:

  A The project is operating at a favorable cost efficiency ratio.

  B the project is spending more than planned

  C the project is behind schedule

  D the project is ahead of schedule

  E B and C

  ans:C

  20 Cost forecasting calculations include:

  A EAC = ACWP + (BAC - BCWP)

  B EAC = BAC/CPI

  C EAC = ACWP + (BAC/CPI)

  D All of the above.

  E A and B

  ans:E

日韩免费va_欧美在线亚洲综合一区_欧美精品与人动性物交免费看_亚洲欧美小说色综合小说一区

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
日韩免费va_欧美在线亚洲综合一区_欧美精品与人动性物交免费看_亚洲欧美小说色综合小说一区
欧美经典一区二区| 欧美日韩国产色站一区二区三区| 欧美日韩美女一区二区| 午夜精品久久久久久| 一区一区视频| 国产乱码精品一区二区三区不卡 | 国产日韩欧美在线播放不卡| 欧美成人在线免费视频| 午夜精品一区二区三区电影天堂 | 久久久久九九九| 欧美在线播放| 99视频精品在线| 亚洲国产成人91精品| 国产一区二区三区网站| 国产精品嫩草影院av蜜臀| 欧美日韩精品一区二区三区| 奶水喷射视频一区| 久久精品日韩一区二区三区| 亚洲欧美国产精品专区久久| 99视频有精品| 亚洲精品1区| 在线成人av网站| 国产真实久久| 国产欧美欧美| 国产精品亚洲综合色区韩国| 欧美日韩视频在线观看一区二区三区| 免费久久99精品国产自在现线| 欧美中文日韩| 久久精品1区| 欧美影院久久久| 欧美亚洲系列| 亚洲在线观看| 亚洲免费在线看| 亚洲天堂激情| 亚洲一区二区三区乱码aⅴ蜜桃女| 亚洲精品乱码久久久久久久久| 亚洲激情在线视频| 亚洲国产岛国毛片在线| 在线观看一区视频| 黑丝一区二区| 在线成人www免费观看视频| 国产亚洲精品久久久久动| 国产一区美女| 韩国一区二区三区在线观看 | 国产欧美日韩精品一区| 国产精品久久二区| 国产精品一区免费观看| 国产精品久久福利| 国产亚洲va综合人人澡精品| 国产日韩欧美二区| 一区在线视频| 亚洲国产福利在线| 日韩视频欧美视频| 日韩一级片网址| 亚洲视频视频在线| 欧美成年视频| 欧美日韩国产成人| 国产精品久久久久秋霞鲁丝| 国产精品亚洲综合色区韩国| 国产精品一香蕉国产线看观看| 欧美日韩国产一区二区三区| 欧美裸体一区二区三区| 欧美高清不卡| 欧美日韩综合久久| 国产精品久久久久久久久久久久| 欧美亚一区二区| 国产精品天天看| 国产一区二区三区在线观看免费| 狠狠色噜噜狠狠色综合久| 亚洲激情视频网站| 夜夜嗨av一区二区三区免费区| 亚洲欧美日韩中文视频| 亚洲视频狠狠| 久久亚洲春色中文字幕久久久| 久久中文字幕导航| 欧美日本亚洲| 国产日韩一区二区三区在线| 一色屋精品视频免费看| 一区二区三区国产在线| 欧美一区二区三区视频免费| 蜜臀va亚洲va欧美va天堂| 麻豆国产va免费精品高清在线| 欧美精品在线视频| 欧美性猛交一区二区三区精品| 国产精品户外野外| 国内精品模特av私拍在线观看| 日韩视频在线一区二区三区| 亚洲男女毛片无遮挡| 男人的天堂亚洲在线| 欧美视频在线一区二区三区| 悠悠资源网久久精品| 亚洲素人在线| 乱中年女人伦av一区二区| 国产精品国产三级国产aⅴ9色| 国产在线精品一区二区夜色| 日韩亚洲国产精品| 久久精品一区二区三区中文字幕| 欧美日韩国产三区| 好看的av在线不卡观看| 亚洲一区国产一区| 美女91精品| 国产一区二区三区久久悠悠色av| 日韩视频永久免费观看| 久久久精品动漫| 国产精品高潮在线| ●精品国产综合乱码久久久久| 亚洲视频欧美视频| 欧美成人免费在线观看| 国产亚洲一级| 中文欧美字幕免费| 欧美激情亚洲激情| 国产精品综合视频| 亚洲一区999| 韩国久久久久| 欧美影院成人| 国产精品美女一区二区在线观看| 亚洲日本国产| 久热精品视频在线| 国产亚洲精品一区二区| 亚洲欧美视频| 欧美日韩精品免费观看| 亚洲人成亚洲人成在线观看图片| 欧美一区二区免费视频| 国产精品swag| 亚洲精品日韩在线观看| 蜜臀av性久久久久蜜臀aⅴ四虎| 国产日本欧洲亚洲| 亚洲在线免费观看| 欧美偷拍另类| 一本久久知道综合久久| 欧美人与性禽动交情品| 亚洲国产精品va在线看黑人动漫| 久久久精品欧美丰满| 国产精品永久免费| 亚洲一区在线观看免费观看电影高清| 欧美高清在线| 精品69视频一区二区三区| 亚洲欧美日本在线| 欧美日韩精品一区视频| 亚洲美女啪啪| 欧美精品国产一区二区| 亚洲国产日韩欧美综合久久 | 亚洲欧美日韩国产一区| 欧美日韩精品免费观看| 亚洲剧情一区二区| 欧美黄色免费网站| 91久久国产综合久久蜜月精品| 麻豆视频一区二区| 国内成人在线| 久久蜜桃资源一区二区老牛| 欧美午夜一区二区福利视频| 国产精品99久久久久久宅男 | 国产精品你懂的在线欣赏| 伊人久久久大香线蕉综合直播| 久久久久久久久久久久久9999| 国产亚洲一区二区三区在线观看 | 国产一区二区三区精品欧美日韩一区二区三区| 亚洲一区二区免费看| 国产精品家教| 亚洲在线网站| 国产欧美精品日韩精品| 亚洲欧美综合| 国产一区二三区| 狼狼综合久久久久综合网| 亚洲国产精品国自产拍av秋霞| 欧美人成免费网站| 一区二区三区精品| 国产精品久久午夜夜伦鲁鲁| 欧美一进一出视频| 一区二区三区无毛| 欧美激情 亚洲a∨综合| 欧美亚洲免费在线| 在线日韩av片| 欧美精品久久一区二区| 一本一本久久a久久精品综合麻豆| 国产精品二区影院| 亚洲欧美在线视频观看| 国内精品美女av在线播放| 麻豆久久久9性大片| 国产精品免费网站在线观看| 久久精品国产成人| 亚洲成在线观看| 欧美日韩在线视频一区| 国产精品丝袜白浆摸在线| 久久se精品一区精品二区| 国产亚洲精品自拍| 美女啪啪无遮挡免费久久网站| 亚洲人成久久| 欧美午夜宅男影院在线观看| 欧美中文日韩| 亚洲精品网址在线观看| 国产精品人人做人人爽人人添| 久久久综合精品| 一区二区三区欧美在线| 国产日韩欧美二区| 欧美激情第10页| 在线中文字幕一区| 一区二区三区在线高清| 欧美视频二区36p| 久久日韩粉嫩一区二区三区|