PMP考試題及參考答案(35)

轉載者:PMP團購網      發布時間:2012/7/24        點擊: 5494

1 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:

  A Multiplying the actual hours worked on the project by the budgeted labor rate.

  B Multiplying the budgeted hours to complete the task by the budgeted labor rate.

  C Dividing the actual hours required to complete the task by the budgeted labor rate.

  D Cannot be determined.

  E None of the above

  ans:B

  2 The methods and techniques for determining the economic costs, the environmental impact, the economic returns, and the probability for success are called:

  A Feasibility studies.

  B Bills of materials.

  C Pert charts.

  D Managerial reserves.

  E None of the above

  ans:A

  3 The planned cost for the total project at its inception is called the _____.

  A Cost of goods sold.

  B Depreciable value.

  C Budgeted cost.

  D All of the above.

  E B and C only.

  ans:C

  4 Which of the following is not a measure of the profitability of a project or program?

  A Return on original investment.

  B Net present value.

  C Depreciation.

  D Discounted cash flow.

  E None of the above

  ans:C

  5 The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.

  A Unauditable.

  B Undistributed.

  C Preauthorized.

  D Contingency.

  E In-process.

  ans:B

  6 Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets?

  A $3,000

  B $27,000

  C $27,270

  D $1,335

  E $1,000

  ans:E

  7 Using the situation stated in the Special window, the labor rate cost variance is:

  A $66,927

  B $68,329

  C $386

  D $-0

  E $18.36

  ans:D

  8 In project-driven companies, costs are usually billed againest the project based upon:

  A The burdened labor rate of the actual employees who performed the work.

  B The burdened labor rate of the line organization average salary.

  C The burdened labor rate of the company average salary.

  D The burdened labor rate of the average salary of the project team members.

  E None of the above.

  ans:A

  9 The most common method for pricing out non-burdened labor hours for a three year project would be to:

  A Price out the hours at the actual salary of the people to be assigned.

  B Price out the work using a company-wide average labor rate.

  C Price out the work using a functional group average labor rate.

  D All of the above.

  E A and B only.

  ans:C

  10 An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:

  A Higher salaried employees were assigned.

  B Overtime was required.

  C The overhead rate increased.

  D Employee salaries had increased.

  E Any of the above

  ans:E

  11 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:

  A The project will be completed late.

  B The critical path has been lengthened.

  C the costs are being overrun.

  D Overtime will be required to maintain the original critical path.

  E None of the above.

  ans:E

  12 Using the situation stated in the Special window, the total price variance of direct material is:

  A $80,245

  B $-4,236

  C $-3,479

  D $1

  E $83,994.00

  ans:C

  13 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.

  A Become worse, become worse

  B Become worse, improved

  C Improved, increased

  D Improved, become worse

  E None of the above are correct

  ans:E

  14 A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called a(n) _____.

  A Trend line.

  B Trend analysis.

  C S curve.

  D Percent completion report.

  E Earned value report.

  ans:C

  15 Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.

  A Over, 16.66

  B Under, 16.66

  C Over, 10.0

  D Under, 10.0

  E None of the above.

  ans:A

  16 Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:

  A 1.1

  B 0.9

  C 0.956

  D 1.15

  E 0.869

  ans:A

  17 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:

  A 0.875

  B 1.14

  C 0.952

  D 0.833

  E 1.2

  ans:B

  18 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

  A Element P

  B Element Q

  C Element R

  D Element S

  E None of the above.

  ans:C

  19 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?

  A Element P

  B Element Q

  C Element R

  D Element S

  E None of the above.

  ans:D

  20 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?

  A Direct labor dollars

  B Direct labor hours.

  C Overhead rates.

  D Procurement costs.

  E None of the above.

  ans:B

日韩免费va_欧美在线亚洲综合一区_欧美精品与人动性物交免费看_亚洲欧美小说色综合小说一区

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
日韩免费va_欧美在线亚洲综合一区_欧美精品与人动性物交免费看_亚洲欧美小说色综合小说一区
欧美影院成年免费版| 亚洲开发第一视频在线播放| 一本色道久久99精品综合| 国产亚洲毛片| 亚洲国产成人在线播放| 午夜综合激情| 欧美日韩综合久久| 国产欧美日韩精品a在线观看| 国产视频亚洲精品| 亚洲精品乱码久久久久久按摩观 | 狠狠综合久久av一区二区老牛| 欧美黄色一区二区| 国产精品扒开腿做爽爽爽视频| 亚洲视频精选| 久久综合九色综合网站| 久久精品国产精品亚洲精品| 国产精品久久久久高潮| 中文在线资源观看网站视频免费不卡 | 欧美日韩综合在线免费观看| 亚洲美女视频| 国产一区二区高清视频| 久久久精品一区| 在线成人激情视频| 欧美色中文字幕| 午夜精品久久久久| 欧美激情网站在线观看| 亚洲人成网站在线播| 欧美精品久久久久久久| 国产日韩欧美a| 欧美黑人在线播放| 在线观看中文字幕不卡| 最新日韩精品| 国产欧美在线观看一区| 欧美精品日韩一本| 免费在线亚洲欧美| 亚洲精品久久久久久久久| 国产人成精品一区二区三| 欧美xxx成人| 麻豆精品视频| 欧美亚男人的天堂| 国产真实久久| 亚洲午夜久久久久久尤物 | 久久青青草原一区二区| 极品日韩av| 欧美日韩一区二区免费视频| 国产亚洲欧洲997久久综合| 欧美成人国产| 久久综合久久88| 久久久噜噜噜久久中文字幕色伊伊 | 亚洲人久久久| 欧美日本亚洲视频| 国产精品vvv| 欧美日韩播放| 国产精品美女久久久浪潮软件| 亚洲国产一区二区a毛片| 亚洲激情视频| 日韩系列欧美系列| 性欧美大战久久久久久久免费观看| 国产日产亚洲精品| 激情婷婷久久| 亚洲免费播放| 先锋影院在线亚洲| 欧美日韩国产a| 国产欧美亚洲视频| 亚洲黄色小视频| 午夜精品免费| 欧美精品在线免费播放| 国内精品久久久久国产盗摄免费观看完整版 | 国产精品久久精品日日| 国内伊人久久久久久网站视频 | 久久综合狠狠综合久久激情| 久久中文字幕一区| 欧美大片免费观看在线观看网站推荐| 亚洲第一综合天堂另类专| 亚洲国产欧美一区二区三区丁香婷| 久久av在线看| 欧美黄色免费| 91久久国产综合久久蜜月精品 | 国产日本精品| 在线日韩中文字幕| 国产欧美日本在线| 在线一区亚洲| 欧美视频在线视频| 老司机精品视频网站| 免费欧美日韩国产三级电影| 亚洲精品乱码| 老司机免费视频一区二区| 亚洲视频一区在线| 欧美精品久久99久久在免费线| 国内精品一区二区三区| 久久亚洲欧美| 国产一区激情| 亚洲影音先锋| 激情久久婷婷| 国产一区二区高清视频| 亚洲一区二区三区四区五区午夜| 日韩亚洲欧美成人| 亚洲精品社区| 久久亚洲综合网| 亚洲欧洲三级电影| 欧美日韩另类字幕中文| 亚洲精品一区二区三区婷婷月| 亚洲精品久久久久久下一站 | 国产综合一区二区| 欧美一区二区视频免费观看| 国产日韩欧美中文| 男女激情视频一区| 久久精品一区中文字幕| 在线观看欧美激情| 欧美激情久久久久| 91久久精品国产91性色| 国产精品久久二区| 欧美黄色一区| 亚洲香蕉伊综合在人在线视看| 在线日韩欧美视频| 亚洲人成绝费网站色www| 久久精品人人做人人爽电影蜜月| 欧美与欧洲交xxxx免费观看 | 日韩亚洲在线| 国内偷自视频区视频综合| 亚洲一区二区免费在线| 亚洲精品国产精品乱码不99| 亚洲国内精品| 亚洲精品午夜| 欧美精品在线观看播放| 91久久线看在观草草青青| 韩国福利一区| 亚洲欧洲在线观看| 99精品黄色片免费大全| 中日韩美女免费视频网址在线观看| 欧美精品一区二区三区很污很色的| 99国产成+人+综合+亚洲欧美| 欧美日韩色综合| 国产精品久久久久久久久久尿 | 亚洲人成77777在线观看网| 黄色日韩网站| 日韩香蕉视频| 性欧美1819性猛交| 女女同性女同一区二区三区91| 亚洲精选视频在线| 在线一区欧美| 久久露脸国产精品| 欧美视频在线观看一区| 国产视频一区免费看| 欧美日韩国产小视频在线观看| 欧美一区二区视频免费观看| 久久一区精品| 国产日韩欧美精品综合| 日韩午夜高潮| 免费欧美在线视频| 国产精品网站在线播放| 伊人狠狠色j香婷婷综合| 亚洲在线观看免费| 久久九九久久九九| 欧美日韩一区二区三区四区在线观看 | 在线观看日韩| 亚洲欧美国内爽妇网| 欧美日韩精选| 在线精品福利| 国产日韩欧美在线看| 亚洲人成免费| 欧美第十八页| 韩国欧美一区| 国产精品拍天天在线| 国产一区二区三区丝袜| 国产精品国产自产拍高清av| 国产精品一区二区欧美| 亚洲国产精彩中文乱码av在线播放| 欧美激情一二区| 国产精品日韩精品欧美精品| 亚洲欧洲日韩综合二区| 欧美一区二区高清| 国产精品久久久久久久久久久久 | 欧美欧美全黄| 黄色成人av网站| 欧美资源在线观看| 国产精品高精视频免费| 亚洲免费久久| 欧美日韩999| 欧美激情一区二区三区在线视频 | 亚洲欧美日韩国产中文| 欧美日韩中国免费专区在线看| 欧美日韩亚洲在线| 亚洲无亚洲人成网站77777| 欧美日韩一区二区三区免费| 国产精品久久久久久久久借妻| 国产精品影音先锋| 久久精品电影| 亚洲精品乱码久久久久久久久| 99在线精品视频| 亚洲欧美日韩一区二区三区在线| 欧美在线亚洲在线| 久久久久在线观看| 麻豆精品在线视频| 99re6热只有精品免费观看| 欧美亚洲第一区| 久久男人资源视频| 一区二区三区日韩精品| 在线成人小视频| 欧美天堂亚洲电影院在线观看|