PMP考試題庫之項目成本管理6-10題:6. Cost Variance (CV) is which of the following equations?
A. CV= BCWP – BCWS
B. CV= BCWP –ACWP
C. CV= SV/BCWS
D. A andC
成本偏差(CV)是下面的哪個公式?
A. CV= BCWP – BCWS
B. CV= BCWP –ACWP
C. CV= SV/BCWS
D. A andC
7. In the following table, which project is most likely to finish ahead of schedule? Project BCWS BCWP ACWP
A 1000 800 600
B 1000 600 800
C 1000 1200 800
A. Project A
B. Project B
C. Project C
D. All three the projects will be completed at the same time
下面的表中,哪個項目最可能會提前完成?
A. 項目A
B. 項目B
C. 項目C
D. 所有三個項目會在同時完成
8. Based on the information in question 7, which will most likely be completed within time and
cost constraints?
A. Project A
B. Project B
C. Project C
D. Both A and B answers
在第七題的基礎下,哪個項目會在時間要求以及成本要求內完成?
A. 項目A
B. 項目B
C. 項目C
D. A 和B
9. Cost budgeting can be best described by which of the following?
A. The process of developing the future trends along with the assessment of probabilities, uncertainties, and inflation that could occur during the project
B. The process of assembling and predicting costs of a project over its life cycle
C. The process of establishing budgets, standards, and a monitoring system by which the investment cost of the project can be measured and managed
D. The process of gathering, accumulating, analyzing, monitoring, reporting, an d managing the costs on an on-going basis.
下面哪個是對成本預算最合適的描述?
A. 制定未來發展趨勢以及評估項目中可能發生的概率、不確定性以及通貨膨脹的過程
B. 對項目在命周期中的成本進行計算和預測的過程
C. 建立預算、標準和檢測系統以進行對項目投資的衡量和管理的過程
D. 在項目進行過程中收集、累計、分析、檢測、報告和管理成本的過程
10. Which of the following is a direct project cost?
A. Lighting and heating for the corporate office
B. Workers Compensation insurance
C. Piping for an irrigation project
D. A andB
下面哪一項是項目直接成本?
A. 公司辦公室的照明和取暖費用
B. 職員的賠償保險
C. 為一個灌溉項目裝管道
D. A 和B
PMP認證考試題參考答案:6-10 BCCCC