PMP考試每天一練--2016年PMP考試模考試題-5
PMP試題5. You are assigned project manager in executing project; the project is in control on baseline, if customers are not satisfied with the performance, then what you should do firstly? A. Discussing with project team B. Baseline revised C. Contract Renegotiation D. Meeting with customers PMP試題5.在項目執行過程中,你被任命為項目經理。項目各項指標都在基線的允許范圍內,如果客戶對項目績效不滿意,你首先應該做什么? A. 與項目團隊一起討論 B. 重新計算基線 C. 重新商談合同 D. 與客戶見面 參考答案:D 考題解析:控制干系人參與工具-會議(13.4.2.3)P413 |