PMP考試每天一練--PMP考試試題-47
PMP考試試題一: Who controls the indirect (overhead) costs of a project? A. Project manager B. Executive management C. Cost accounts manager D. Internal auditor 是誰控制一個項目的間接成本(管理費)? A. 項目經理 B. 高級管理層 C. 成本帳目經理 D. 內部審計員 PMP參考答案:B. 高級管理層 PMP答案解析:成本分類-間接成本 PMP考試試題二: During the Define Activities process, a team member begins to discuss activities that the project manager has never heard discussed. What should the project manager do? A. Make sure he has a good understanding of the activities and include the activities in the activity list. B. Ask the team member to explain why such an activity would be needed to complete the work package. C. Make sure the entire team agrees that the activities should be done. D. Evaluate the impact of the change. 在定義活動過程中,一團隊成員開始討論一個項目經理從來沒有聽過的活動。此時項目經理應該怎么做? A.確保團隊成員理解并將這些活動包含在活動清單里了。 B.詢問團隊成員需要完成這些活動的原因。 C.確認所有團隊成員都認同這些活動。 D.評估變更的影響。 審題: 此題的關鍵字為“定義活動”“討論”,項目進入規劃階段的范圍管理中的定義活動過程 定位: 規劃過程組·時間管理·6.2 定義活動 解析: 1、定義活動過程的目的是對活動(為完成工作包而必須開展的工作)進行定義,項目經理需要確認該活動是必須開展的;因此本題答案為B; 2、選項A活動清單是定義活動過程的輸出,排除;選項C是WBS的作用,排除;選項D為監控過程組的工作,排除; 3、此題的場景是干擾項,對選擇沒有作用,解題需要了解定義活動的目的和活動的定義。 答案:B.詢問團隊成員需要完成這些活動的原因。 |