PMP考試試題一: What is the goal of a quality audit on a project? A. Deliver higher quality products for the same price. B. Rate the quality of a process C. Identify inefficient and ineffective processes. D. Report project quality to the sponsor. 項(xiàng)目質(zhì)量審計(jì)的目標(biāo)是什么? A. 以同樣的價(jià)格提供更高質(zhì)量的產(chǎn)品。 B. 對(duì)過(guò)程的質(zhì)量評(píng)級(jí) C. 識(shí)別低效率和無(wú)效的過(guò)程 D. 將項(xiàng)目質(zhì)量報(bào)告給發(fā)起人 PMP參考答案:C. 識(shí)別低效率和無(wú)效的過(guò)程 PMP答案解析:質(zhì)量審計(jì)目的 (8.2.2.2)P247 PMP考試試題二: John is managing a mufti-phase project and needs to validate the previous phase's assumptions and decisions in order to determine if the business needs for the project still exist. Referring to the scenario above, which one of the following processes does John need to follow to accomplish this goal? A. Monitoring and Controlling Process B. Initiating Process C. Closing Process D. Executing Process 約翰管理一個(gè)多階段的項(xiàng)目,需要驗(yàn)證前一階段的假設(shè)和決策,以便判斷項(xiàng)目的商業(yè)需求是否依然存在。完成這一目標(biāo),約翰處于哪一個(gè)過(guò)程? A. 監(jiān)控過(guò)程。 B. 啟動(dòng)過(guò)程。 C. 收尾過(guò)程。 D. 執(zhí)行過(guò)程。 審題: 關(guān)鍵詞“多階段”和“驗(yàn)證前一階段的假設(shè)和決策”和“以便判斷項(xiàng)目的商業(yè)需求”一般是項(xiàng)目啟動(dòng)時(shí)要做的工作,但是整個(gè)項(xiàng)目完成了幾個(gè)階段了,是否仍然是啟動(dòng)過(guò)程呢? 定位: 啟動(dòng)過(guò)程組·項(xiàng)目管理框架·3.3 啟動(dòng)過(guò)程組 解析: 確定前一階段的工作已確認(rèn)是否可以進(jìn)入后已階段,按照各階段為一個(gè)項(xiàng)目的原則,約翰完成的目標(biāo)是在項(xiàng)目的啟動(dòng)階段。 PMP參考答案:B. 啟動(dòng)過(guò)程。 |