PMP考試試題一: The project team is required to comply with government regulations and union contracts. The project manager has identified the strategy for its implementation. Which plan should be updated with this strategy? A.Staffing management plan B.Risk management plan C.Project management plan D.Communication management plan 項(xiàng)目團(tuán)隊(duì)被要求遵守政府法規(guī)和勞工合同。項(xiàng)目經(jīng)理已經(jīng)確定了實(shí)施戰(zhàn)略。下列哪一項(xiàng)計劃應(yīng)跟隨戰(zhàn)略更新? A.人員配備管理計劃 B.風(fēng)險管理計劃 C.項(xiàng)目管理計劃 D.溝通管理計劃 PMP參考答案:A.人員配備管理計劃 PMP答案解析:人員配備管理計劃-合規(guī)性 (9.1.3.1) P265 PMP考試試題二: You are having difficulty estimating the cost of a project. Which of the following BEST describes the most probable cause of your difficulty? A.Inadequate scope definition. B.Unavailability of desired resources. C.Lack of historical records from previous projects. D.Lack of company processes. 你在做成本估算時遇到了困難,以下哪項(xiàng)是出現(xiàn)困難的最可能原因? A.缺乏確定的范圍。 B.沒有提供預(yù)期的資源。 C.缺乏以前項(xiàng)目的歷史數(shù)據(jù)。 D.公司缺少流程。 審題:造成成本估算困難,可以理解為輸入出現(xiàn)了問題。回憶成本估算過程的幾個輸入,用排除法找到對該過程影響最大、最根本的因素。 定位:規(guī)劃過程組·成本管理·估算成本 解析: 1、項(xiàng)目的歷史數(shù)據(jù)和流程都屬于組織過程資產(chǎn),這項(xiàng)輸入只是估算的參考數(shù)據(jù),可能會增加成本估算的難度,但不會是導(dǎo)致困難的根本原因,因此C、D不對。 2、沒有獲得預(yù)期的資源可能會導(dǎo)致估算精度不夠,但是依然會有一個大概的答案,因此B不對。 3、算的前提是范圍明確。因此答案為A。如果范圍定義不清楚,也就是沒有一個確定的范圍基準(zhǔn),那么將無法進(jìn)行任何估算。 PMP參考答案:A. 缺乏確定的范圍。 |