PMP考試每天一練--PMP考試試題99
PMP考試試題一: Progressive elaboration is a characteristic of projects that integrate the concepts of temporary and unique in project plan development, progressive elaboration also is terms of A. Assumptions B. Constraints C. Project management information system D. Organizational policies and procedures 漸進明細是結合了項目的一次性和獨特性的特點。編制項目計劃的過程中,漸進明細在以下哪個方面也是重要的: A. 假設 B. 限制條件 C. 項目管理信息系統 D. 組織政策和程序 PMP參考答案:A. 假設 PMP答案解析:項目范圍說明書-項目假設條件(5.3.3.1 ) P124 PMP考試試題二: A project team is having difficulty communicating over long distances. There were 13 team members from two countries, and then five people from India were added. This is of concern to the project manager because: A. Communications channels grow rapidly. B. It will be harder to use reward power. C. Communication blockers grow linearly. D. Conflict can be increased with an increase in project priorities. 項目團隊在遠距離溝通上遇到了困難,13位團隊成員來自不同的2個國家,后來又增加了5位來自印度的成員。這應該引起項目經理的關注,因為: A. 溝通渠道迅速增加。 B. 使用獎勵權力變得更困難。 C. 溝通阻礙者以直線的速度增加。 D. 項目優先級的增加導致沖突的增加。 審題: 此題的關鍵字為“遠距離溝通上遇到了困難”和“增加了5為成員”,題干描述遠程溝通的困難和人員增加的情況。 定位: 規劃過程組.溝通管理·10.1.2 規劃溝通管理: 工具和技術 解析: 此題主要解決的是溝通人員增加帶來的溝通渠道增加的問題,選項A正確。 資源的增加一般不會增加使用獎勵權力(選項B)的難度。選項C的描述本身就不正確。選項D在題干中沒有涉及。 PMP參考答案:A. 溝通渠道迅速增加。 |