PMP考試每天一練--PMP考試試題107
PMP考試試題一: In planning your project, which would generally have the highest priority; quality, cost or schedule? A. Cost is most important, quality next, and then schedule. B. Quality is more important than cost or schedule. C. Schedule is most important, quality next, and then cost. D. It should be decided for each project. 編制項(xiàng)目計(jì)劃時(shí),質(zhì)量、成本和進(jìn)度哪個(gè)最為重要? A. 成本最重要,質(zhì)量次之,最后是進(jìn)度計(jì)劃 B. 質(zhì)量最重要 C. 進(jìn)度計(jì)劃最重要,質(zhì)量次之,最后是成本 D. 應(yīng)根據(jù)不同的項(xiàng)目來決定 PMP參考答案:D. 應(yīng)根據(jù)不同的項(xiàng)目來決定 PMP答案解析:項(xiàng)目制約因素( 1.3 )P6 PMP考試試題二: At a critical design review meeting for a large project, several important issues surfaced. After hearing about a major technical problem, one of the subcontractor's engineers mentions that he experienced a similar situation on another project; he has some ideas on how to solve the current problem. What type of power is the engineer using? A. Manipulate. B. Formal. C. Expert. D. Referent. 在一個(gè)大型項(xiàng)目的關(guān)鍵設(shè)計(jì)評(píng)審會(huì)議上出現(xiàn)了一些重要的問題。在聽完這些關(guān)鍵技術(shù)問題后,一位承包商的工程師說他曾經(jīng)經(jīng)歷過類似的事情,并對(duì)問題提出了相關(guān)的解決建議。這位工程師使用的是何種權(quán)力? A.控制。 B.正式。 C.專家。 D.潛示。 審題: 此題的關(guān)鍵字為“曾經(jīng)經(jīng)歷過類似的事情、對(duì)問題提出了相關(guān)的解決建議”,那他就是對(duì)處理這個(gè)問題有經(jīng)驗(yàn)的人。 定位: 執(zhí)行過程組·人力資源管理·9.2.2.2 組建團(tuán)體:工具和技術(shù) 解析: 這位工程師以前遇到過類似的問題,他比別人更具備解決此類問題的知識(shí),所以他使用的是專家權(quán)力。 |