PMP考試每天一練--PMP考試試題109
PMP考試試題一: To complete a process, phase, or project, which of the following must be approved? A. Budgets B. Deliverables C. Resources D. Schedules 若要完成一個過程,階段或項目,必須獲得下列哪一項的批準? A. 預算 B. 可交付成果 C. 資源 D. 進度表 PMP參考答案:B. 可交付成果 PMP答案解析:結束項目或階段引言(4.6) P100 PMP考試試題二: You are in charge of a project developing a complex product that does not resemble anything your organization has done previously. You are using a resource to develop this product that is in high demand elsewhere in your organization. The project’s timeframe is very aggressive. In order to meet the schedule, only a limited amount of testing is done. Once the testing is completed, the resource is released. The product works fine when being tested, but in production, it performs poorly. This results in a substantial amount of rework and extra costs to reacquire the resource on an overtime basis. Which of the following BEST describes why this project had problems? A. Poor quality management. B. Poor reporting. C. Poor risk identification. D. Poor resource management. 你負責的項目是開發一個復雜的產品,而且你們公司之前沒有做過類似的項目。你需要某一專業人員來開發這個產品,但這位專業人員在公司很搶手。項目的工期很緊,為了符合進度,測試部分只實施了一小部分,測試完成后,該專業人士就被調離了項目。測試的時候產品一切正常,但投入生產時就出了問題。這導致了大量的返工,并增加了額外成本,因為需要這位專業人員加班工作。以下哪項描述了可能產生此問題的原因? A.質量管理較差。 B.報告系統很差。 C.風險識別的較差。 D.資源管理較差。 審題: 此題的關鍵字為“測試部分只實施了一小部分,測試完成后,該專業人士就被調離了項目,需要這位專業人員加班工作”,隱含著風險問題。 定位: 規劃過程組·項目人力資源管理·制定人力資源計劃 解析: 項目對某一專業人員的依賴性較強,題干描述問題反映出人力資源計劃不健全;為符合進度而只實施部分的測試,從而為生產時問題的發生埋下隱患。綜合來看,問題的原因產生自資源管理較差。 PMP參考答案:D.資源管理較差。 |