PMP考試每天一練--PMP考試試題178
PMP考試試題一:
What function does the staffing management plan serve? A. It describes project roles and responsibilities. B. It is an organization chart that shows which organizational units are responsible for which work packages. C. It describes when and how human resources will be brought and taken off of the project team. D. It contains written outlines by job title of the competencies,responsibilities, and authority of a given job. 人員配備管理計劃有什么功能? A.它描述項目角色和責任。 B.它是一份組織圖,表明哪個組織單位負責哪個工作細目 C. 它描述人力資源何時、如何加入和退出項目團隊。 D.它包括有給定工作的資格、職責、權限的工作名稱構成的書面大綱。 PMP答案解析:人員配備管理計劃 (9.1.3.1) P265 PMP參考答案:C.它描述人力資源何時、如何加入和退出項目團隊 PMP考試試題二: You are working with a group of managers to decide which projects to pursue. Cost is an important consideration.Whick type of costs should not be a criteria in project selection? A.Indirect costs. B.Sunk costs. C.Tangible costs. D.Intangible costs. 你和一個經理團隊一起決定進行哪一些項目,成本是重要的考慮因素,下面哪一項不是項目選擇的標準? A.直接成本。 B.沉沒成本。 C.有形成本。 D.無形成本。 審題:此題解題的關鍵是找到題干關鍵句“決定進行”、 “不是” 定位:成本管理的拓展。 PMP參考答案:B.沉沒成本 |