PMP考試每天一練--PMP考試試題190
PMP考試試題一: The project manager invites stakeholders to a project status review. The communication management plan includes 12 members.There are requests to include for 2 members. How many additional communication channels are required? A. 6 B. 27 C. 66 D. 120 項目經(jīng)理邀請干系人參加項目狀態(tài)評審。溝通管理計劃中包含12名成員。同時額外請求增加2名干系人。那么還需要多少個額外溝通渠道? A. 6個 B. 27個 C. 66個 D. 120個 PMP答案解析:規(guī)劃溝通管理工具-溝通需求分析( 10.1.2.1 )P292 PMP參考答案:B. 27個 PMP考試試題二: A project manager has run into cost difficulties. the project scope must be completed, but at less cost. the project manager should: A. Change the depreciation method for the equipment used on the project. B. Perform a value analysis. C. Evaluate benefit cost ratios. D. Recover some sunk costs. 項目經(jīng)理的成本出現(xiàn)了問題,但項目范圍還必須完成。在缺乏成本的情況下,項目經(jīng)理應(yīng)該: A. 更改項目對設(shè)備折舊的方法 B. 進(jìn)行價值分析 C. 評估收益成本比率 D. 恢復(fù)部分沉淀成本 審題:此題目在關(guān)鍵句為“缺乏成本”“范圍必須完成” 定位:項目成本管理 PMP參考答案:C. 評估收益成本比率 |