PMP考試每天一練--PMP考試試題200
PMP考試試題一: Which process is integration management performed? A. Project planning B. Project executing C. At key interface points D. At the end of each project management phase 項目整合管理應該發生在哪個階段? A. 項目規劃階段 B. 項目執行階段 C. 在關鍵接口點 D. 在項目管理的每個階段結束 PMP答案解析:項目整合管理引言 P63 PMP參考答案:C PMP考試試題二: A company defines a high level description of a new project. What should the project manager do to develop the project scope? A. direct the project team to collect technical requirements B. takes no action, as the project manager is not yet assigned to the project C. agree with the project sponsor regarding the budget assigned to the project D. conduct working sessions with the customer to better understand project expectations 一家公司定義一個新項目的高層次描述。為了制定項目范圍,項目經理應該怎么做? A. 指示項目團隊收集技術需求 B. 不采取任何行動,因為項目經理還未任命到項目上 C. 就分配到項目的預算方面與項目發起人達成一致意見 D. 與客戶召開工作會議,以便更好地理解項目期望 PMP答案解析:理解項目期望才能明確范圍邊界、定義高層次范圍。 PMP參考答案:D |