PMP考試練習(xí)題一: After the identification of a technical risk, the project manager decides to hire a senior resource to join the project team. What risk response strategy does the project manager use? A.Mitigate B.Identify C.Accept D.Expert judgment 在識別完一項技術(shù)風(fēng)險后,項目經(jīng)理決定雇傭一名高級資源加入項目團(tuán)隊。項目經(jīng)理使用的是什么風(fēng)險應(yīng)對策略? A.減輕 B.識別 C.接受 D.專家判斷 PMP答案解析:雇傭更高級的資源,這是減輕。 PMP參考答案:A PMP考試練習(xí)題二: A project manager is managing a US$5 million fixed-price project that has had many changes to the scope. As a part of the business requirements session, the business architect identifies a change that will involve 100 hours of additional requirements analysis.To document the change, the business architect should create which of the following? A. Project document updates, work performance information, and project management plan updates B. Project document updates, change request, and scope baseline C. Change request, team performance assessments, and project management plan updates D. Organizational process assets updates, communications management plan, and change request 項目經(jīng)理正在管理一個價值500萬美元的固定總價項目,該項目對范圍做了許多變更。作為業(yè)務(wù)需求會的組成部分,業(yè)務(wù)架構(gòu)師確定了一項變更,該變更將涉及100小時的額外需求分析。 A.項目文件更新,工作績效信息和項目管理計劃更新 B.項目文件更新,變更請求和范圍基準(zhǔn) C.變更請求,團(tuán)隊績效評估和項目管理計劃更新 D.組織過程資產(chǎn)更新,溝通管理計劃和變更請求 PMP答案解析:和變更有關(guān)的,只有B選項合適。 PMP參考答案:B |