PMP考試每天一練-2018年PMP考試試題21
PMP考試試題一: After a review of a company’s completed project, the company learns the integrity of the data could not be sufficiently verified. Which of the following should have helped to avoid this issue? A.Lessons learned B.Quality audit C.Project scope management D.Proper document archiving 在審查一家公司的已完成項目后,公司認識到數據的完整性不能得到充分合適。下列那一項對避免這個問題有幫助? A.經驗教訓 B.質量審計 C.項目范圍管理 D.正確的文檔存檔 PMP答案解析:數據不完整說明文件、文檔有缺失,要避免這個問題需要進行正確的文件歸檔。 PMP參考答案:D PMP考試試題二 To date, the project has been progressing smoothly. A new project manager is assigned and there is a disagreement with a vendor on the amount and price of the work completed.Which document should the project manager consult to determine work to be completed? A.Statement of work B.Negotiated contract C.Procurement plan D.Notice to proceed 到目前為止,項目進展順利。任命了一名新項目經理,與供應商對已完成工作的金額和價格存在分歧。項目經理應查閱哪一份文件確定已完成的工作 A.工作說明書 B.協商合同 C.采購計劃 D.繼續進行的通知 PMP答案解析:合同中包括了工作說明書或可交付成果描述 PMP參考答案:B |