PMP考試每天一練-2018年PMP考試試題22
PMP考試試題一: An ongoing project is on schedule when a subject matter expert (SME) on the project's critical path requests three days off, what should the project manager do? A. Initiate a change request through performs integrated change control process. B. Send a change request to the change control board (CCB) for approval. C. Persuade the SME to work as planned; if unsuccessful, update the project management plan. D. Identify this as a resource risk that is out of control, and update the risk register. 一個正在進行的項目正按進度計劃進行,這時一名在項目關鍵路徑上的主題專家(SME)請求請三天假。項目經理應該怎么做? A.通過執行整體變更控制過程提出變更請求。 B.向變更控制委員會(CCB)發送一份變更請求批準。 C.說服SME按計劃工作:如果不成功,則更新項目管理計劃。 D.將其識別為失控的資源風險,更新風險登記冊。 PMP答案解析:關鍵路徑上的資源變更可能引起進度基準的變更,這是個風險。先查看有無應急儲備,如果實在沒辦法才提變更 PMP參考答案:D PMP考試試題二 After project implementation, the project management office (PMO) inquires whether the project’s business objective was achieved. To address the question, what should the project manager do? A. Conduct a customer satisfaction survey B. Review the project charter with the project sponsor C. Conduct a variance analysis D. Conduct a post-project review 項目實施后,項目管理辦公室(PMO)詢問是否已實現項目的商業目標。若要解決這個問題,項目經理應該怎么做? A.開展客戶滿意度調查 B.與項目發起人一起審查項目章程 C.執行偏差分析 D.進行項目后評價 PMP答案解析:項目章程中有可衡量的目標 PMP參考答案:B |