PMP考試每天一練-2018年PMP考試試題31
PMP考試試題一: During project closure, a vendor did not fulfill a contractual obligation to submit mandatory documentation, which leads to a dispute. What should the project manager do to settle the dispute with the vendor? A.Leverage gain-sharing B.Record the dispute in the project documents C.Settle the dispute in a court of law D.Seek alternate dispute resolutions 在項目收尾期間,供應商未履行提交強制性文檔的合同義務,最終導致糾紛。若要解決與供應商的糾紛,項目經理應該怎么做? A.利用收益分享 B.在項目文件中記錄該糾紛 C.在法院中解決該糾紛 D.采取其他糾紛解決方案 PMP答案解析:若要解決糾紛有三個方法,順序為: 1、友好協商:比如談判。 2、ADR 替代爭議解決:比如調解、仲裁。 3、訴訟 PMP參考答案:D PMP考試試題二 During the project execution phase, a project manager learns that the customer’s organization could be acquired by another organization. What should the project manager do next? A.Revisit the project charter B.Perform a risk reassessment C.Ask for the project sponsor’s guidance D.Discuss the issue with stakeholders 在項目執行階段,項目經理了解到客戶所在組織可能被另一個組織收購。項目經理下一步該怎么做? A.查看項目章程 B.執行風險再評估 C.尋求項目發起人的知道 D.與干系人討論這個問題 PMP答案解析:客戶所在組織可能被另一個組織收購,風險較大,需要對風險再評估 PMP參考答案:B |