PMP考試每天一練-2018年P(guān)MP考試試題45
PMP考試試題一: A project team installs a new operating system. Before implementation, the team tests the system on a smaller, isolated network and discovers some issues. After finding solutions to these issues, the team still encounters implementation issues. However, the number and severity of issues are greatly reduced Which of the following does the project team use? A.Transferring risk B.Mitigating risk C.Accepting risk D.Avoiding risk 項(xiàng)目團(tuán)隊(duì)安裝一個(gè)新的操作系統(tǒng)。實(shí)施之前,該團(tuán)隊(duì)在一個(gè)較小獨(dú)立的網(wǎng)絡(luò)中測試該系統(tǒng),并發(fā)現(xiàn)一些問題。發(fā)現(xiàn)這些問題的解決方案之后,團(tuán)隊(duì)仍然碰到實(shí)際問題。然后,問題數(shù)量和嚴(yán)重程度大大降低。項(xiàng)目團(tuán)隊(duì)使用的是下列哪一項(xiàng)? A.轉(zhuǎn)移風(fēng)險(xiǎn) B.減輕風(fēng)險(xiǎn) C.接受風(fēng)險(xiǎn) D.規(guī)避風(fēng)險(xiǎn) PMP答案解析:團(tuán)隊(duì)先在一個(gè)較小獨(dú)立的網(wǎng)絡(luò)中測試。問題數(shù)量和嚴(yán)重程度大大降低,這是減輕風(fēng)險(xiǎn) PMP參考答案:B PMP考試試題二 A sponsor provides inaccurate and outdated information to the board of directors regarding the project’s overall progress. To prepare the sponsor for future updates to the board of directors, what should the project manager do first? A.Issue an updated project schedule to the sponsor and highlight the changes B.Meet with the sponsor and determine all reporting requirements C.Prepare daily project status reports for the sponsor D.Update the project communications management plan 發(fā)起人向董事會提交的項(xiàng)目總體進(jìn)度相關(guān)信息不準(zhǔn)確且過時(shí)。為了讓發(fā)起人做好未來向董事會提交更新的準(zhǔn)備,項(xiàng)目經(jīng)理首先應(yīng)該做什么? A.向發(fā)起人發(fā)送一份更新的項(xiàng)目進(jìn)度計(jì)劃,并重點(diǎn)突出任何變化 B.與發(fā)起人開會,確定所有報(bào)告要求 C.為發(fā)起人準(zhǔn)備每日項(xiàng)目狀態(tài)報(bào)告 D.更新項(xiàng)目溝通管理計(jì)劃 PMP答案解析:題干說到相關(guān)信息不準(zhǔn)確且過時(shí),溝通出了問題,應(yīng)該更新溝通管理計(jì)劃 PMP參考答案:D |