PMP考試每天一練-2019年PMP考試試題183
PMP考試試題一: The project manager is informed by the company’s internal auditor that the project documentation must be reviewed at the next quality audit. What is the purpose of this audit? A.Verify that the production quality meets customer expectations B.Check that the company’s quality process is followed C.Ensure the company’s processes align with ISO 9001 D.Meet process improvement recommendations 公司內部審計員通知項目經理必須在下一次質量審計時審查項目文檔。該審計的目的是什么? A.驗證產品質量是否符合客戶期望 B.檢測是否遵循公司的質量過程 C.確保公司的過程符合ISO9001 D.滿足過程改進建議 PMP答案解析:質量審計是用來確定項目活動是否遵循了組織和項目的政策、過程與程序。 PMP參考答案:B PMP考試試題二 During project initiation, a key stakeholder claims the project is no longer viable. What should the project manager do to evaluate the project’s viability? A. Refer the stakeholder to the project sponsor. B. Delay reassessment until project funding is exhausted at the end of initiation. C. Check alignment with the business case and present to sponsor and key stakeholders. D. Start the project closure process immediately. 在項目啟動期間,一名關鍵干系人聲稱項目不再可行。為評估項目的可行性,項目經理應該怎么做? A.將該干系人推薦給項目發起人。 B.拖延項目再評估,直至項目資金在啟動階段結束時用完。 C.檢查是否與商業論證保持一致,并提交給項目發起人和關鍵干系人。 D.立即開始項目收尾過程。 PMP答案解析:再進行商業論證,評估可行性。 PMP參考答案:C |