PMP考試每天一練-2020年PMP考試練習題128
PMP考試練習題一: A project sponsor implements a new document control process. This new process will delay access to information, which will lead to increased labor costs and schedule delay. How should the project manager integrate this new process? A.Use the risk management plan to evaluate the risk and report back to the project sponsor B.Propose a more efficient document control process for use on the project C.Implement the new requirements using the change management plan D.Schedule a meeting with project stakeholders for a risk urgency assessment 一個項目發起人落實一項新的文件控制流程。這項新流程將延遲對項目的訪問,將導致人工成本增加及進度延遲。項目經理應該如何整合這項新流程? A.使用風險管理計劃評估風險,并向項目發起人報告 B.想出更為有效的文件控制流程用于項目 C.使用變更管理計劃實施心需求 D.與項目關系人安排一次會議,進行風險緊迫性評估 PMP考試答案解析:將導致人工成本增加及進度延遲,說明這是風險,排除C。 PMP考試參考答案:A PMP考試練習題二 A key user representative involved in product validation activities proposes changes to some tasks and deliverables outlined in the project's methodology. These changes would considerably impact the validation strategy defined during the planning phase.What should the project manager do first? A. Remove the key user representative from the validation team B. Include the project management office (PMO) in the discussion C. Send an e-mail to the key user representative with the agreed-upon methodology outlined in the planning phase D. Maintain authority and ensure the validation strategy is executed as planned 參與產品核實活動的一名關鍵用戶代表提出對項目方法中所述的一些任務和可交付成果進行變更,這些變更將對規劃階段所定義的核實策略造成相當大的影響。項目經理首先應該做什么? A.將該關鍵用戶代表從核實團隊開除 B.將項目管理辦公室(PM0)包含進討論中 C.向關鍵用戶代表發送一封電子郵件,并附上規劃階段中所述的約定方法 D.保留職權,并確保按計劃執行核實策略 PMP考試答案解析:關鍵用戶提出對項目管理方法中的一些內容進行大的變更,PM應該把PMO也包含進討論中。因為PMO的職能是給予項目提供指導、輔導、監督,制定項目管理方法以及識別最佳實踐。 PMP考試參考答案:B |