PMP考試每天一練-2018年PMP考試試題47
PMP考試試題一: The customer of a delayed project requests an additional feature. The feature can be built with no significant impact to the schedule or cost.What should the project manager do next? A.Accept the proposal as compensation to the customer for the project delay B.Deny the request immediately without further consultation C.Put the feature on hold, as a future enhancement D.Create a change request and submit to the change control board for consideration 某個延期項目的客戶請求增加功能。該功能可以在不對進度或成本產生重大影響的情況下嵌入。項目經理下一步該怎么做? A.接受該提議作為對客戶項目延期的補償 B.在不進一步咨詢的情況下,立即拒絕該請求 C.擱置該功能,作為未來改進功能 D.創建一份變更請求,并將其提交給變更控制委員會考慮 PMP答案解析:直接接受、直接拒絕、擱置,都是不對的,排除ABC。應該遵循變更管理流程首先提交變更請求 PMP參考答案:D PMP考試試題二 The management team identifies a new risk that could potentially delay to a deliverable by six weeks. In response to this, what should the project manager do first? A. Quantity the impact B. Analyze the variance C. Update the risk register D. Implement corrective actions 管理團隊識別可能會延遲某個可交付成果六周時間的新風險。為應對這種情況,項目經理應該首先做什么? A. 量化影響 B. 分析偏差 C. 更新風險登記冊 D. 執行糾正措施 PMP答案解析:識別到新風險,首先應該更新到風險登記冊中 PMP參考答案:C |